Construction Begins on March 25, 2013....Please attempt to avoid the center of town between the hours of 7 AM through 5 PM. The roads that will be affected during the construction are Main Street, Old Bridge Street, Marsh Road, Nashua Road, and Acorn Lane....April 15th - April 19th Acorn Lane will be the only road closed to all traffic.

ROUNDABOUT PROJECT UPDATE

5/28/2013

 

  • Waterline work is currently underway in the vicinity of the Congregational Church. 

  • The old fire station is completely demolished and all demo debris has been removed. 
     

  • Water line tie-in is planned for Friday night (5/31). Continental will notify impacted residents of procedure to flush their water lines. The tie-in is scheduled for evening hours to minimize service interruptions. 
     

  • Next week (Week of June 3rd), Continental will do fine grading in preparation for base and binder coats of asphalt along Marsh Road and Town roundabout. 
     

  • Following week (week of June 10) base and binder paving along Marsh and Town roundabout, with some curbing and sidewalk installation (tentative).
     

  • The balance of Acorn binder paving on hold until Continental can get it scheduled (week of June 3rd hoped for).  Some utility conduit exists on Acorn at Woodbury that must be removed but is dependent on Fairpoint splicing their relocated aerial lines and pulling new line through new conduit.
     

  • Old Bridge Street and Blacksmith Road name changes would be ideally be resolved by end of June. NHDOT, may prefer to utilize temporary signage (pre-name change) over the winter until project is fully completed. I have informed NHDOT that we will need to coordinate the new road name activation date with corresponding signage placement as part of the BOS public hearing process.
     

  • Continental will continue working until end of July or early August before they no longer proceed without Fairpoint’s utility work being completed. There is no indication these issues will be resolved in time to avoid that outcome. In this scenario, Continental will likely not return until the spring of 2014 , assuming Fairpoint can finally get their work coordinated and completed between August and the spring of 2014. 

If you have any questions about the roundabout project, please contact Jeff Gowan at the Planning Department at 635-7188 or e-mail him at jgowan@pelhamweb.com

For more Information on the project visit the Project Specific Information site at the link below:

http://www.nh.gov/dot/projects/pelham14491/index.htm