RSA 674:75 Advanced Pipeline Notification

In order to comply with RSA 674:75 the landowner/developer must email with the address and map of the area to the following email address:

KMEncroachmentsNorth@kindermorgan.com

They will either respond back with an email stating that they don’t have facilities within the project limits as stated in the email or map, or if they do have facilities they will respond with additional instructions.

These instructions will include filling out the encroachment information form and providing them with a fill set of plans for their review and approval. They will also send the developer handbook.

The typical review and approval process takes 6 to 10 weeks to complete depending on response times from landowner/developer and complexity. Once approved they will issue a developer approval letter that will outline the conditions of approval.

See the full RSA below:

674:75 Advance Pipeline Notification. –
I. As used in this section, " natural gas transmission pipeline " means an interstate pipeline, as that term is defined in 15 U.S.C. Section 3301(15); and
II. For a new residential or nonresidential development that is located in whole or in part within 1,000 feet of the center point of a natural gas transmission pipeline that was constructed or operated prior to the development, the applicant shall notify the operator of the natural gas transmission pipeline of the planned development no later than the time of application for approval of the development, or 180 days prior to commencement of construction, whichever is earlier.
III. The developer of the development shall provide on a form filed with the local land use board the following notice:
"All reasonable means were used to obtain information about natural gas transmission pipeline facilities in the area of the proposed development and pipeline operator(s) were contacted to verify the location of the pipeline and the pipeline easement. The developer has reviewed, or attempted to review, preliminary information about the proposed development with the pipeline operator."
IV. Within 60 days of the effective date of this section, a local land use board in a municipality that is within 1,000 feet of the center point of a natural gas transmission pipeline shall make National Pipeline Mapping System geospatial data available to developers from the Pipeline and Hazardous Materials Safety Administration within the United States Department of Transportation relative to the locations of pipelines.
V. Upon receiving notice of a planned development in accordance with this section, a pipeline operator shall locate and mark the natural gas pipeline facilities and provide pipeline facility information to the developer by other means such as marking up design drawings and providing maps.
VI. A building permit shall not be issued, and a building shall not be erected on a lot within the jurisdiction of a local land use board unless one of the following 3 criteria is met:
(a) The developer has received written consent from the natural gas pipeline operator and has filed this consent with such regional planning commission;
(b) The developer has not received written consent from the natural gas pipeline operator, but has filed with such local land use board written correspondence from the pipeline operator demonstrating that discussions and outreach have occurred; or
(c) The developer has filed dated and written correspondence with such local land use board that demonstrates attempts to contact the natural gas pipeline operator and that no response has been received within 180 days of the filing.
VII. This section applies only to counties and municipalities that are governed by a local land use board for purposes of approving residential and nonresidential developments.